Customer :

Gate Terminal Bv

Role :

EPC Contractor

Key date :

January 2008 to September 2011

Location :

Rotterdam, The Netherlands

Description of the Project

Teams from VINCI Construction Grands Projets, Entrepose Contracting, Freyssinet, and Soletanche Bachy worked for 3 years to develop the Gate Terminal, located in the port of Rotterdam. The terminal was inaugurated on September 23, 2011 with Queen Beatrix of the Netherlands in attendance.

Project management: Ashghal, Public Works Authority

Work done and added value of our solution

It includes 3 LNG storage tanks with a capacity of 180,000 m3. The facility can contribute 12 billion m3 of natural gas to the gas-distribution network. A plant and 2 methane-carrier unloading docks were also built at this site.